Zhejiang Double Arrow Rubber Co., Ltd.
With the annual throughput of 100,000,000 tonnes, which occupies 1/3 throughput of Zhoushan port area, Ningbo-Zhoushan Port Qushan Harbour Area Shuliang Lake ore transshipment terminal has become a handle of wharf who has the direct land capacity of 400,000tonnes of ore ships. It marked the first time in the south of the Yangtze River to unload the world’s largest ore ship, and the dry bulk cargo went into the “Super Wheel Era”.
Double Arrow supplied the following product for this project.(engineering use)
ST1250 1800*(7+5+5) 2280m
ST2000 1800*(8+6+6) 4060m
ST2500 1800*(8+7.2+6)20180m
EP300 1800*6(6+3) 745m
The two uploaders in discharging berth can discharge 6,000tonnes of ore per hour. A total of more than 120,000 tonnes of ore can be completed in one day. Through the conveyor belt on the corridor, the ore can be transported directly from the unloading dock to the loading dock or to the depot.